Prepare for a new electricity meter

Once the new supply to your property has been installed, or your existing supply is approved for an additional load, you will need to get your supply connected to a meter.

Step by step:

  • Once supply works are complete and paid for in full, your electrician needs to complete a Connection of Meter form
  • Request a new domestic supply either by phone, email or online

OR

  • Complete an Application for Commercial Electricity Supply form
  • Return the form(s) marked New Installation Technician by:
    • Email meter@jec.co.uk
    • Hand or post to: Jersey Electricity, The Powerhouse, Queens Road, St Helier JE4 8NY
    • By hand to The Power Station, La Collette
  • On receipt, we will endeavour to install a meter within five working days
  • We will contact you be telephone to arrange access if necessary

For further information on supply connection, call 505711.
 

Downloads
Application For A Supply Of Electricity To Non-Domestic Premises
Connection of Meter form