Information update for customers following Storm Austen

Information update for customers following Storm Austen

As we continue the recovery from Storm Austen, our teams have made good progress restoring supplies across the Island.

- 133 customers were affected across 20 separate incidents.
- Just 19 customers remain without power, with teams working to resolve the final three network issues today, weather permitting.
- We expect all remaining customers to be restored and back on supply today.
- Thank you to our teams and contractors for their hard work and to customers for their patience and understanding.

Should you experience any issues with the electricity network over the weekend

- Please stay well clear of any damaged electrical equipment or power infrastructure.
- Report any electricity hazards by calling our emergency line on 01534 505050.
- Vulnerable customers without power are asked to contact our Customer Care team on 01534 505460. 

The Energy Blog N1 cable route planners make final checks for UXO

The last remaining survey work on the inshore areas of the Normandie 1 (N1) cable route here off Archirondel and off the French coast at St Remy des Landes is complete and Jersey Electricity’s route planners are now analysing the data for natural obstacles, terrain features and metal objects, including WW2 unexploded ordnance, that could pose problems for the installation of the new 100MW subsea cable later this summer.

The last remaining survey work on the inshore areas of the Normandie 1 (N1) cable route here off Archirondel and off the French coast at St Remy des Landes is complete and Jersey Electricity’s route planners are now analysing the data for natural obstacles, terrain features and metal objects, including WW2 unexploded ordnance, that could pose problems for the installation of the new 100MW subsea cable later this summer.

Though most of the 27km route was surveyed over several weeks last July and August, the remaining stretches could not be done until the old, decommissioned EDF1 cable had been successfully recovered from the seabed. This work was completed in April by Hughes Sub Surface Engineering of Merseyside which was awarded the contract to safely remove, recycle where possible and dispose of the cable, in accordance with JE’s environmental and regulatory obligations.

JE CEO Chris Ambler said: ‘We are delighted that this hazardous offshore work has been successfully completed and the N1 project as a whole remains on target. We always strive to ensure best value for Jersey Electricity and for our customers. In this case, the works were tendered and, written into the Invitation-to-Tender, were the rights to the scrap value of the old cable. The scrap value thus helped to offset the cost of removing the cable from the seabed.’